PMI-SP · Question #211
Yolanda is the project manager for her organization. She is creating a performance report for her sponsor. Typically, the performance report includes all of the following factors except for which one?
The correct answer is B. Quality control activities. Quality control activities are not included in the performance report, but are documented in the quality management plan. A performance report is made by the project team detailing activities, milestones, problems, accomplishments, and identified issues. Performance reports are…
Question
Yolanda is the project manager for her organization. She is creating a performance report for her sponsor. Typically, the performance report includes all of the following factors except for which one?
Options
- ACurrent status of risk and issues
- BQuality control activities
- CAnalysis of past performance
- DWork to be completed next
How the community answered
(56 responses)- A5% (3)
- B91% (51)
- C2% (1)
- D2% (1)
Explanation
Quality control activities are not included in the performance report, but are documented in the quality management plan. A performance report is made by the project team detailing activities, milestones, problems, accomplishments, and identified issues. Performance reports are used to report some key information as follows: Current status Scheduled activities Significant accomplishment for the period Forecasts Issues Answer option C is incorrect. Analysis of past performance can be included in the performance report to make the report more elaborate. Answer option A is incorrect. Current status of risk and issues can be included in the performance Answer option D is incorrect. Work to be completed next can be included in the performance
Topics
Community Discussion
No community discussion yet for this question.