PMI-SP · Question #102
Which of the following is an output of the Identify Stakeholders process?
The correct answer is D. Stakeholder register. The Identify Stakeholders process identifies all people or organizations that are impacted by the project. It also documents relevant information regarding their interests, involvement, and impact on project success. Stakeholder register and stakeholder management strategy are…
Question
Which of the following is an output of the Identify Stakeholders process?
Options
- AScope baseline
- BProject scope statement
- CProject charter
- DStakeholder register
How the community answered
(43 responses)- A9% (4)
- B2% (1)
- C2% (1)
- D86% (37)
Explanation
The Identify Stakeholders process identifies all people or organizations that are impacted by the project. It also documents relevant information regarding their interests, involvement, and impact on project success. Stakeholder register and stakeholder management strategy are outputs of Answer option C is incorrect. Project charter is one of the inputs of the Identify Stakeholders Answer option A is incorrect. Scope baseline is one of the outputs of the Create Work Breakdown Structure (WBS) process. Answer option B is incorrect. Project scope statement is one of the outputs of the Define Scope