PMI
PMI-SP · Question #103
PMI-SP Question #103: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #103. The question stem and answer options stay visible for context.
Question
Examine the figure given below: You are the project manager of this project. Tom, a project team member, reports that Activity D will be delayed by 12 days due to the unavailability of the resources from the vendor. What will this delay do to your project completion, if you allow the delay to enter into the project?
Exhibit
Options
- AThe project will be one day late.
- BThe float for activity D will be consumed.
- CThe project can still finish on time.
- DThe project will be seven days late.
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
