nerdexam
PMI

PMI-SP · Question #101

PMI-SP Question #101: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #101. The question stem and answer options stay visible for context.

Question

Allen works as a project manager of the NHY project. This project is scheduled to last for two years and has a BAC of $5,400,000. He is currently 45 percent complete with this project, though he is supposed to be at his second milestone, which accounts for half of the project completion. There have been some errors in the project, which have caused Allen to spend $2,093,754. What is this project's schedule variance?

Options

  • A
    • $210,000
  • B
    • $720,000
  • C
    • $250,000
  • D
    • $270,000

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice