PMI-SP · Question #100
You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other…
The correct answer is C. Project schedule network diagrams. The project schedule network diagram is an output of the sequence activity process, not an input. This process uses five inputs: the activity list, the activity attributes, milestone list, the project scope statement, and the organizational process assets. The project schedule…
Question
You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?
Options
- AProject scope statement
- BMilestone list
- CProject schedule network diagrams
- DActivity list
How the community answered
(46 responses)- A2% (1)
- B2% (1)
- C91% (42)
- D4% (2)
Explanation
The project schedule network diagram is an output of the sequence activity process, not an input. This process uses five inputs: the activity list, the activity attributes, milestone list, the project scope statement, and the organizational process assets. The project schedule network diagram is an output of the sequence activity process. It represents a schematic display of the project's schedule activities and the logical relationship among them. This diagram can be produced manually or by using the project management software. It consists of complete project details, or one or more summary activities. Answer options D, B and A are incorrect. These are inputs to the process.