PMI-SP · Question #34
Which may be employed to shorten a schedule without changing the scope of the task?
The correct answer is D. Fast tracking. You've hit your limit · resets 5am (America/New_York)
Schedule Planning and Development
Question
Which may be employed to shorten a schedule without changing the scope of the task?
Options
- AAlter to task priorities.
- BReleasing resources earlier from tasks which were scheduled with a late start.
- CFast tracking or Crashing
- DFast tracking.
- ECrashing
How the community answered
(31 responses)- A6% (2)
- C3% (1)
- D87% (27)
- E3% (1)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#fast tracking#schedule compression#crashing#scope preservation