PMI-SP · Question #34

Which may be employed to shorten a schedule without changing the scope of the task?

The correct answer is D. Fast tracking. You've hit your limit · resets 5am (America/New_York)

Schedule Planning and Development

Question

Which may be employed to shorten a schedule without changing the scope of the task?

Options

  • AAlter to task priorities.
  • BReleasing resources earlier from tasks which were scheduled with a late start.
  • CFast tracking or Crashing
  • DFast tracking.
  • ECrashing

How the community answered

(31 responses)
  • A
    6% (2)
  • C
    3% (1)
  • D
    87% (27)
  • E
    3% (1)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#fast tracking#schedule compression#crashing#scope preservation