nerdexam
PMI

PMI-SP · Question #115

You are the project manager for your organization. Your project will need four electrical engineers for the project though there are no electrical engineers within your department. This scenario is…

The correct answer is C. Resource requirement. This is an example of a resource requirement. The project needs four electrical engineers even though the resources are not within your department. Your organization could be a matrix structure, or it could hire resources from outside the organization. Answer option D is…

Schedule Planning and Development

Question

You are the project manager for your organization. Your project will need four electrical engineers for the project though there are no electrical engineers within your department. This scenario is best described as which one of the following terms?

Options

  • AAssumption
  • BRisk
  • CResource requirement
  • DResource constraint

How the community answered

(40 responses)
  • B
    3% (1)
  • C
    95% (38)
  • D
    3% (1)

Explanation

This is an example of a resource requirement. The project needs four electrical engineers even though the resources are not within your department. Your organization could be a matrix structure, or it could hire resources from outside the organization. Answer option D is incorrect. A resource constraint is evident when the project requires the electrical engineer and she is not available. A requirement, as in this scenario, is simply the identification of the needed resource even if the resource is not available in your department. Answer option B is incorrect. This is not an example of a risk, unless the resource is constrained by other projects, schedules, or work and may not be available at all when needed. Answer option A is incorrect. An assumption would be believing the resource is available for the project without confirming the availability of the

Topics

#resource requirements#resource planning#activity resource estimating#project constraints

Community Discussion

No community discussion yet for this question.