Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project…

The correct answer is B. Scope baseline. All scope changes should also be updated in the project scope baseline. The scope baseline is the project scope statement, work breakdown structure (WBS), and the WBS dictionary. Answer option D is incorrect. If the changes affect cost then the cost baseline would also be…

Schedule Monitoring and Controlling

Question

Vicky is the project sponsor of Robert's project. She has requested several changes for the project scope and these changes have, of course, been approved. Robert needs to incorporate the project scope changes into the activity list. Where else should Robert reflect these project changes?

Options

  • AProject final report
  • BScope baseline
  • CQuality control mechanism
  • DCost baseline

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    92% (22)
  • C
    4% (1)

Explanation

All scope changes should also be updated in the project scope baseline. The scope baseline is the project scope statement, work breakdown structure (WBS), and the WBS dictionary. Answer option D is incorrect. If the changes affect cost then the cost baseline would also be updated. The question did not indicate that therbe would a change in the project cost. Answer option C is incorrect. Quality control does not change. It always reflects the demands of the project scope. Answer option A is incorrect. The project final report evaluates the success and failures of the

Topics

#scope baseline#scope change management#change integration#activity list updates