PMI-SP · Question #117
PMI-SP Question #117: Real Exam Question with Answer & Explanation
The correct answer is D. Costs are lower than planned.. According to the question, the cost variance of the project is 30, which is a positive figure. A positive value means that cost is less than planned. What is CV? Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are higher than budge
Question
Options
- AProject is behind the schedule.
- BCosts are higher than planned.
- CCosts are right on target.
- DCosts are lower than planned.
Explanation
According to the question, the cost variance of the project is 30, which is a positive figure. A positive value means that cost is less than planned. What is CV? Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are higher than budgeted or lower than budgeted. The cost variance is calculated based on the following formula: CV = Earned Value (EV) - Actual Cost (AC) A positive value means that spending is less than budgeted, whereas a negative value indicates that costs are higher than originally planned for the project. Answer option C is incorrect. If the CV is zero, it shows that cost is right on target. Answer option A is incorrect. This result is depicted by viewing the schedule variance (SV), not Answer option B is incorrect. If the CV is a negative value, it depicts that the costs are higher than
Community Discussion
No community discussion yet for this question.