nerdexam
PMI

PMI-SP · Question #117

You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?

The correct answer is D. Costs are lower than planned. According to the question, the cost variance of the project is 30, which is a positive figure. A positive value means that cost is less than planned. What is CV? Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are higher than…

Schedule Monitoring and Controlling

Question

You work as a project manager for BlueWell Inc. You are calculating the performance indexes of your project. The cost variance (CV) of your project is 30. What does this figure depict?

Options

  • AProject is behind the schedule.
  • BCosts are higher than planned.
  • CCosts are right on target.
  • DCosts are lower than planned.

How the community answered

(56 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    7% (4)
  • D
    88% (49)

Explanation

According to the question, the cost variance of the project is 30, which is a positive figure. A positive value means that cost is less than planned. What is CV? Cost variance (CV) is a measure of cost performance on a project. The variance notifies if costs are higher than budgeted or lower than budgeted. The cost variance is calculated based on the following formula: CV = Earned Value (EV) - Actual Cost (AC) A positive value means that spending is less than budgeted, whereas a negative value indicates that costs are higher than originally planned for the project. Answer option C is incorrect. If the CV is zero, it shows that cost is right on target. Answer option A is incorrect. This result is depicted by viewing the schedule variance (SV), not Answer option B is incorrect. If the CV is a negative value, it depicts that the costs are higher than

Topics

#cost variance#earned value management#CV interpretation#schedule performance

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice