PMI-SP · Question #197

PMI-SP Question #197: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #197. The question stem and answer options stay visible for context.

Question

You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

Options

  • AIt is derived from the constraints of the project.
  • BIt is assigned to the project by management.
  • CIt is created by the stakeholders.
  • DIt is developed from the schedule network analysis.

Unlock PMI-SP to see the answer