PMI
PMI-SP · Question #197
PMI-SP Question #197: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #197. The question stem and answer options stay visible for context.
Question
You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?
Options
- AIt is derived from the constraints of the project.
- BIt is assigned to the project by management.
- CIt is created by the stakeholders.
- DIt is developed from the schedule network analysis.
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.