nerdexam
PMI

PMI-SP · Question #207

You are project manager of HHK project. Examine the network diagram given below: A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #207. The question stem and answer options stay visible for context.

Schedule Planning and Development

Question

You are project manager of HHK project. Examine the network diagram given below:

A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?

Exhibit

PMI-SP question #207 exhibit

Options

  • AFour days
  • BSix days
  • CFive days
  • DZero, it is on the critical path.

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#float calculation#network diagram#activity delay#schedule analysis
Full PMI-SP Practice