PMI-SP · Question #207
You are project manager of HHK project. Examine the network diagram given below: A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based…
The correct answer is A. Four days. Activity E has four days of float. The entire project will take 19 days to complete. Float, also called slack, is the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available: Free Float: It is the amount of…
Question
You are project manager of HHK project. Examine the network diagram given below:
A vendor reports that he will be four days late on the materials you'll need in order to complete Activity E. Based on the project network diagram, how many days can Activity E be delayed?
Exhibit
Options
- AFour days
- BSix days
- CFive days
- DZero, it is on the critical path.
How the community answered
(46 responses)- A61% (28)
- B7% (3)
- C11% (5)
- D22% (10)
Explanation
Activity E has four days of float. The entire project will take 19 days to complete. Float, also called slack, is the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available: Free Float: It is the amount of time a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Total Float: It is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating schedule constraint. Float is calculated by using the critical path method technique. Answer option D is incorrect. Activity E is not on the critical path. Answer options C and B are incorrect. These are incorrect calculations of the amount float available for Activity
Topics
Community Discussion
No community discussion yet for this question.