nerdexam
PMI

PMI-SP · Question #267

Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure for twenty- four hou

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #267. The question stem and answer options stay visible for context.

Schedule Planning and Development

Question

Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure for twenty- four hours. Fred has arranged these tasks with a finish to start relationship between the priming and the painting. What else should Fred do to account for the twenty-four hours of cure time?

Options

  • AFred should add twenty-four hours of lead time to each of the 456 rooms painting activity to
  • BFred should add twenty-four hours of lag time to each of the 456 rooms painting activity to
  • CFred should add an intermediary task with a duration of twenty-four hours.
  • DFred should schedule all 456 hotels rooms to be primed first and then schedule all 456 rooms

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#lag time#finish-to-start#dependency types#schedule sequencing
Full PMI-SP Practice