nerdexam
PMI

PMI-SP · Question #267

PMI-SP Question #267: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #267. The question stem and answer options stay visible for context.

Question

Fred is the project manager of a hotel restoration project. The hotel has 456 rooms. All rooms need to be primed and painted. Before each room can be painted, the primer must cure for twenty- four hours. Fred has arranged these tasks with a finish to start relationship between the priming and the painting. What else should Fred do to account for the twenty-four hours of cure time?

Options

  • AFred should add twenty-four hours of lead time to each of the 456 rooms painting activity to
  • BFred should add twenty-four hours of lag time to each of the 456 rooms painting activity to
  • CFred should add an intermediary task with a duration of twenty-four hours.
  • DFred should schedule all 456 hotels rooms to be primed first and then schedule all 456 rooms

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice