PMI-SP · Question #268

You work as a project manager for Honeywell Inc. You have been distributing performance information, including status reports, progress measurement, and forecasts to various stakeholders. A trainee…

The correct answer is B. WPM C. WPI. According to the scenario, you can use the following inputs in order to generate performance WPI: Work performance information is the data gathered on the status of the project schedule activities that are performed to accomplish the project work. This data is collected as part…

Stakeholder Communication

Question

You work as a project manager for Honeywell Inc. You have been distributing performance information, including status reports, progress measurement, and forecasts to various stakeholders. A trainee of this company wants to know what are the inputs for generating performance reports. Which of the following are the necessary inputs? Each correct answer represents a part of the solution. Choose two.

Options

  • AVariance analysis
  • BWPM
  • CWPI
  • DChange request

How the community answered

(52 responses)
  • A
    2% (1)
  • B
    94% (49)
  • D
    4% (2)

Explanation

According to the scenario, you can use the following inputs in order to generate performance WPI: Work performance information is the data gathered on the status of the project schedule activities that are performed to accomplish the project work. This data is collected as part of the Direct and Manage Project Execution processes. WPI includes the following: Deliverables status Schedule Progress WPM: Work performance measurements are created from the work performance information. WPMs are an output of Control schedule, Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs consist of planned versus actual performance indicators with respect to scope, schedule, and cost. They are documented and communicated to the stakeholders and are used to make project activity metrics, such as the following: Planned vs. Actual Technical performance and Scope performance Planned vs. Actual Schedule Planned vs. Actual Cost performance Answer option A is incorrect. Variance analysis is an after-look at what caused a difference between the baseline and the actual performance. It is one of the tools and techniques used for report performance. Answer option D is incorrect. Change requests are requests to expand or reduce the project scope, modify policies, processes, plans, or procedures, modify costs or budgets or revise schedules. These requests for a change can be direct or indirect, externally or internally initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that only formally documented requested changes are processed and only approved change requests are

Topics

#performance reporting#work performance information#inputs#reporting process