The correct answer is D. Corrective action. This is an example of corrective action. The project team will fix the mistake and they have learned from their mistake so it won't happen again. Answer option C is incorrect. Risk mitigation is defined as monies spent or actions taken to reduce the probability and impact of an i
Question
Options
- ARisk response
- BTeam development
- CRisk mitigation
- DCorrective action
Explanation
This is an example of corrective action. The project team will fix the mistake and they have learned from their mistake so it won't happen again. Answer option C is incorrect. Risk mitigation is defined as monies spent or actions taken to reduce the probability and impact of an identified risk event. Answer option A is incorrect. A risk response is an action to counteract an identified risk. Answer option B is incorrect. There may be some team development happening in this instance but we don't have enough information to know for certain. Team development is an activity that brings the whole team cohesion, interdependency, and trust.
Community Discussion
No community discussion yet for this question.