PMI-SP · Question #269

PMI-SP Question #269: Real Exam Question with Answer & Explanation

The correct answer is D. Corrective action. This is an example of corrective action. The project team will fix the mistake and they have learned from their mistake so it won't happen again. Answer option C is incorrect. Risk mitigation is defined as monies spent or actions taken to reduce the probability and impact of an i

Question

Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?

Options

  • ARisk response
  • BTeam development
  • CRisk mitigation
  • DCorrective action

Explanation

This is an example of corrective action. The project team will fix the mistake and they have learned from their mistake so it won't happen again. Answer option C is incorrect. Risk mitigation is defined as monies spent or actions taken to reduce the probability and impact of an identified risk event. Answer option A is incorrect. A risk response is an action to counteract an identified risk. Answer option B is incorrect. There may be some team development happening in this instance but we don't have enough information to know for certain. Team development is an activity that brings the whole team cohesion, interdependency, and trust.

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice