nerdexam
PMI

PMI-SP · Question #270

PMI-SP Question #270: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #270. The question stem and answer options stay visible for context.

Question

You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?

Options

  • ACost, with a variance of -$8,000
  • BSchedule, with a variance of -$33,750
  • CCost, with a variance of $278,000
  • DSchedule, with a variance of -$20,000

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice