PMI-SP · Question #98
You are the project manager of a research project. Because much of the project work will be based on what is discovered in each stage of the project work, you are directing the project time to focus…
The correct answer is B. Rolling wave planning. This is an example of rolling wave planning. Rolling wave planning focuses on the most imminent work in detail and creates estimates for the whole project and later work in broad estimates. Rolling wave planning is a form of progressive elaboration. Rolling wave planning is a…
Question
You are the project manager of a research project. Because much of the project work will be based on what is discovered in each stage of the project work, you are directing the project time to focus on creating time estimates for the most imminent research work and broad estimates for the project work that is coming later in the project. What type of planning are you using in this project?
Options
- AMilestone planning
- BRolling wave planning
- CPhase gates
- DDecomposition
How the community answered
(43 responses)- A2% (1)
- B93% (40)
- C5% (2)
Explanation
This is an example of rolling wave planning. Rolling wave planning focuses on the most imminent work in detail and creates estimates for the whole project and later work in broad estimates. Rolling wave planning is a form of progressive elaboration. Rolling wave planning is a technique for performing progressive elaboration planning where the work to be accomplished in the near future is planned in detail at a low level of the work breakdown structure. The work to be performed within another one or two reporting periods in the near future is planned in detail as work is being completed during the current period. Answer option D is incorrect. Decomposition describes the breakdown of the project scope into work packages, and then the work packages are broken down into project activities. Answer option C is incorrect. Phase gates describe the review process associated with the end of project Answer option A is incorrect. Milestone planning defines the project milestones, not the activities required to reach the milestones.