Lara has been assigned to a construction project. The project includes constructing a residential building with fifty flats. On which of the following events will the project be considered successful?
Options
- AThe project meets or exceeds the expectations of the stakeholders.
- BThe building is complete and handed over to the authority concerned.
- CThe keys of the first flat are handed over to the owner of the flat.
- DSuccessful possession of all flats is made.