PMI-SP · Question #96

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule…

The correct answer is B. 0.75. The schedule performance index is found by dividing the earned value by the planned value. In this instance, the planned value is ten percent more than where the project is forty percent of the budget at completion. Schedule performance index (SPI) is the measure of schedule…

Schedule Monitoring and Controlling

Question

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

Options

  • A$227,140
  • B0.75
  • C0.95
  • D-$56,789

How the community answered

(70 responses)
  • A
    13% (9)
  • B
    77% (54)
  • C
    3% (2)
  • D
    7% (5)

Explanation

The schedule performance index is found by dividing the earned value by the planned value. In this instance, the planned value is ten percent more than where the project is forty percent of the budget at completion. Schedule performance index (SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future performance. SPI is the ratio of earned value to planned value. The SPI is calculated based on the following formula: SPI = Earned Value (EV) / Planned Value (PV) If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value is less than 1, it shows poor performance. The SPI value of 1 indicates that the project is right on target. Answer option C is incorrect. 0.95 is the project's cost performance index. Answer options A and D are incorrect. An index is a decimal value.

Topics

#SPI#earned value management#schedule performance index#BAC