PMI-SP · Question #95
Choose and reorder the essential steps required in developing the scheduling framework. Select an item from the right pane. Click button to move the selected item to the left pane. Click button to mov
The correct answer is A. Determine how the schedule model will be developed. B. Understand the full scope of the project. C. Identify the project and schedule. D. Establish project calendars and work periods. E. Establish the optimal project update cycle. F. Design an effective activity coding structure. G. Determine resource planning requirements.. You've hit your limit · resets 5:20am (America/New_York)
Schedule Planning and Development
Question
Choose and reorder the essential steps required in developing the scheduling framework. Select an item from the right pane. Click button to move the selected item to the left pane. Click button to move the item back to the right pane. Click and buttons to sort the list, if required. Answer:
Exhibits
Options
- ADetermine how the schedule model will be developed.
- BUnderstand the full scope of the project.
- CIdentify the project and schedule.
- DEstablish project calendars and work periods.
- EEstablish the optimal project update cycle.
- FDesign an effective activity coding structure.
- GDetermine resource planning requirements.
How the community answered
(18 responses)- A100% (18)
Explanation
You've hit your limit · resets 5:20am (America/New_York)
Topics
#scheduling framework#schedule development process#planning sequence#schedule strategy