You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following information except for which

The correct answer is B. Project management team's classification. The stakeholder register does not contain the project management team's classification information. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the project and

Stakeholder Communication

Question

You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following information except for which one?

Options

  • AStakeholder classification
  • BProject management team's classification
  • CAssessment information
  • DIdentification information

How the community answered

(23 responses)
  • B
    91% (21)
  • C
    4% (1)
  • D
    4% (1)

Explanation

The stakeholder register does not contain the project management team's classification information. The stakeholder register is a project management document that contains a list of the stakeholders associated with the project. It assesses how they are involved in the project and identifies what role they play in the organization. The information in this document can be very perceptive and is meant for limited exchange only. It also contains relevant information about the stakeholders, such as their requirements, expectations, and influence on the project. Answer options D, C, and A are incorrect. These are the parts of the stakeholder register.

Topics

#stakeholder register#stakeholder classification#identification information#assessment information