Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a schedule baseline…

The correct answer is A. The schedule management plan describes how the schedule will be managed and controlled. The schedule management plan is the intent of the project manager. It defines how the schedule will be managed and controlled. The schedule baseline is a benchmarking tool to compare actual results against the planned results. Answer options C, D, and B are incorrect. These are…

Schedule Planning and Development

Question

Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a schedule baseline. What is the difference between the schedule management plan and the schedule baseline?

Options

  • AThe schedule management plan describes how the schedule will be managed and controlled.
  • BThe schedule management plan describes how the schedule will be managed and controlled.
  • CThe schedule baseline describes how the schedule will be managed and controlled. The
  • DThe schedule management plan describes how the schedule will be created. The schedule

How the community answered

(55 responses)
  • A
    91% (50)
  • B
    2% (1)
  • C
    5% (3)
  • D
    2% (1)

Explanation

The schedule management plan is the intent of the project manager. It defines how the schedule will be managed and controlled. The schedule baseline is a benchmarking tool to compare actual results against the planned results. Answer options C, D, and B are incorrect. These are not valid definitions of the schedule management plan and the schedule baseline.

Topics

#schedule management plan#schedule baseline#schedule control#planning documents