PMI-SP · Question #311

You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for…

The correct answer is D. Identification of project risks. Identification of the project risks is not part of the process improvement plan. Identify risks is a risk management process, and risks are recorded in the risk register. Answer options A, B, and C are incorrect. Process boundaries, Process configuration and Targets for…

Schedule Strategy

Question

You are the project manager of the GHY Project. Management wants you to create a process improvement plan for your project. Your project will be studied by management and will become a standard for all future organizational projects based on your project's performance, approach, and implementation of project processes. All of the following should be included in your project's process improvement plan except for which one?

Options

  • AProcess boundaries
  • BProcess configuration
  • CTargets for improved performance
  • DIdentification of project risks

How the community answered

(16 responses)
  • A
    6% (1)
  • B
    6% (1)
  • C
    13% (2)
  • D
    75% (12)

Explanation

Identification of the project risks is not part of the process improvement plan. Identify risks is a risk management process, and risks are recorded in the risk register. Answer options A, B, and C are incorrect. Process boundaries, Process configuration and Targets for improved performance are parts of the process improvement plan.

Topics

#process improvement plan#process boundaries#process configuration#performance targets