Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is B. Contract C. Business case D. Project statement of work. The Develop Project Charter process documents the formal authorization of a project or a phase. It also documents initial requirements that satisfy the stakeholder's needs and expectations. It is used to validate the decisions made during the previous iteration of the Develop…

Schedule Strategy

Question

Which of the following are the inputs to the Develop Project Charter process? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AProcurement document
  • BContract
  • CBusiness case
  • DProject statement of work

How the community answered

(21 responses)
  • A
    10% (2)
  • B
    90% (19)

Explanation

The Develop Project Charter process documents the formal authorization of a project or a phase. It also documents initial requirements that satisfy the stakeholder's needs and expectations. It is used to validate the decisions made during the previous iteration of the Develop Project Charter process. The various inputs of this process are as follows: Project statement of work Business Enterprise environmental factors Organizational process assets The output of the Develop project Charter process is as follows: Answer option A is incorrect. Procurement document is the input of the Identify Stakeholders

Topics

#project charter#project initiation#procurement document#SOW