nerdexam
PMI

PMI-SP · Question #319

Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal…

The correct answer is D. Activity resource requirements. Because the activities in Beth's project require Tim and his skills. This is an example of an activity resource requirement. A resource constraint would also have been an acceptable answer. Answer option B is incorrect. This may be a matrix organization, but matrix network is…

Schedule Planning and Development

Question

Beth is the project manager for the NHQ project. This project deals with fiber optic cabling in her organizational campus. Tim is the electrical engineer for her company and is the only internal resource that can complete several of the project activities that deal with the fiber optic cables. Because Tim is a highly-skilled resource, he is already scheduled on several projects within the organization and is not available when Beth needs him to complete some of the project activities. This is an example of which term?

Options

  • AResource calendar conflict
  • BMatrix network
  • COrganizational process assets
  • DActivity resource requirements

How the community answered

(31 responses)
  • B
    3% (1)
  • C
    3% (1)
  • D
    94% (29)

Explanation

Because the activities in Beth's project require Tim and his skills. This is an example of an activity resource requirement. A resource constraint would also have been an acceptable answer. Answer option B is incorrect. This may be a matrix organization, but matrix network is not a valid project management term. Answer option C is incorrect. Organizational process assets are things that have been created to help assist the management of the project. Answer option A is incorrect. A resource calendar conflict is not a valid project management term.

Topics

#activity resource requirements#resource constraints#resource calendar#schedule planning

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice