PMI
PMI-SP · Question #321
PMI-SP Question #321: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #321. The question stem and answer options stay visible for context.
Question
John works as a Project Manager for Blue Well Inc. He is measuring cost efficiency of his project. The key values are provided in the table below: What is the cost performance index (CPI) of the project at the current point of time?
Options
- A0.96
- B1.082
- C0.833
- D1.0625
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.