PMI-SP · Question #331
You are a project manager for a documentary film company. In light of a recent regional tragedy, the company president wants to get a new documentary on the rescue efforts of the heroic rescue teams…
The correct answer is B. The primary constraint is quality because the president wants this to be the best film ever. You've hit your limit · resets 5am (America/New_York)
Question
You are a project manager for a documentary film company. In light of a recent regional tragedy, the company president wants to get a new documentary on the rescue efforts of the heroic rescue teams to air as soon as possible. She's looking to you to make this documentary the best that has ever been produced in the history of this company. She guarantees you free rein to use whatever resources you need to get this project done quickly. However, the best photographer in the company is currently working on another assignment. Which of the following is true?
Options
- AThe primary constraint is time because the president wants the film done quickly. She told you
- BThe primary constraint is quality because the president wants this to be the best film ever
- CThe schedule is the primary constraint. Even though the president has given you free rein on
- DResources are the primary constraint. Even though the president has given you free rein on
How the community answered
(42 responses)- A14% (6)
- B76% (32)
- C2% (1)
- D7% (3)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
Community Discussion
No community discussion yet for this question.