PMI-SP · Question #332
A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What…
The correct answer is B. -$200. You've hit your limit · resets 5am (America/New_York)
Schedule Monitoring and Controlling
Question
A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
Options
- A-$700
- B-$200
- C+$200
- D+$500
How the community answered
(21 responses)- A5% (1)
- B81% (17)
- C14% (3)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#cost variance#earned value management#EV#AC
Community Discussion
No community discussion yet for this question.