nerdexam
PMI

PMI-SP · Question #332

A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What…

The correct answer is B. -$200. You've hit your limit · resets 5am (America/New_York)

Schedule Monitoring and Controlling

Question

A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

Options

  • A-$700
  • B-$200
  • C+$200
  • D+$500

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    81% (17)
  • C
    14% (3)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#cost variance#earned value management#EV#AC

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice