nerdexam
PMI

PMI-SP · Question #332

PMI-SP Question #332: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #332. The question stem and answer options stay visible for context.

Question

A work package has been scheduled to cost $1,000 to complete, and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?

Options

  • A-$700
  • B-$200
  • C+$200
  • D+$500

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice