How is scheduled variance calculated using the earned value technique?

The correct answer is C. EV less PV. You've hit your limit · resets 5am (America/New_York)

Schedule Monitoring and Controlling

Question

How is scheduled variance calculated using the earned value technique?

Options

  • AEV less AC
  • BAC less PV
  • CEV less PV
  • DAC less EV

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    88% (37)
  • D
    7% (3)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#schedule variance#earned value technique#EV#PV