PMI-SP · Question #334

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

The correct answer is B. It is a term used to describe activities whose effort can be directly measured and linked to the. Discrete effort is a term used to describe the work that can be measured and traced to the components in the work packages. It is the actual work to create the project deliverables. Discrete effort refers to the particular work effort that can be identified and traced as having…

Schedule Planning and Development

Question

Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?

Options

  • AIt is a term used to describe activities whose effort cannot be directly measured to the project
  • BIt is a term used to describe activities whose effort can be directly measured and linked to the
  • CIt is a term used to describe activities that are supportive of the project work, but not linked to
  • DIt is a term used to describe activities that are core project management processes, but not

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    88% (22)
  • D
    8% (2)

Explanation

Discrete effort is a term used to describe the work that can be measured and traced to the components in the work packages. It is the actual work to create the project deliverables. Discrete effort refers to the particular work effort that can be identified and traced as having a direct tie to the final completion of the project- related work breakdown structure components and the deliverables. It is necessary that all the efforts have a specific measurable end product or end Answer options A, D, and C are incorrect. These are not valid definitions of discrete effort.

Topics

#discrete effort#activity list#work breakdown structure#activity types