nerdexam
PMI

PMI-SP · Question #335

PMI-SP Question #335: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #335. The question stem and answer options stay visible for context.

Question

Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

Options

  • A48
  • B55
  • C54
  • D40

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice
Lily works as a project manager for BlueWell Inc. She has recorded... | PMI-SP Q#335 Answer | NerdExam