nerdexam
PMI

PMI-SP · Question #335

Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will sh

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #335. The question stem and answer options stay visible for context.

Schedule Planning and Development

Question

Lily works as a project manager for BlueWell Inc. She has recorded the following duration estimates for an activity in her project: optimistic 35, most likely 50, and pessimistic 95. What time will she record for this activity?

Options

  • A48
  • B55
  • C54
  • D40

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#three-point estimating#PERT#duration estimates#beta distribution
Full PMI-SP Practice