Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to…

The correct answer is C. Whomever the communications management plan directs her to. The communications management plan will define who will receive what information. Answer option B is incorrect. The project sponsor may be a recipient but the project communications management plan is the best selection. Answer option A is incorrect. Functional management is…

Schedule Close-Out

Question

Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?

Options

  • AFunctional Management
  • BProject sponsor
  • CWhomever the communications management plan directs her to
  • DProject customer

How the community answered

(34 responses)
  • A
    9% (3)
  • B
    12% (4)
  • C
    76% (26)
  • D
    3% (1)

Explanation

The communications management plan will define who will receive what information. Answer option B is incorrect. The project sponsor may be a recipient but the project communications management plan is the best selection. Answer option A is incorrect. Functional management is not the best choice in a projectized Answer option D is incorrect. The project customer may receive a copy of the report, but the project communications management plan should direct the communications.

Topics

#administrative closure#final project report#communications management plan#projectized structure