PMI-SP · Question #120
PMI-SP Question #120: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #120. The question stem and answer options stay visible for context.
Question
You are the project manager for your organization. Management has offered you a bonus if you can complete the project work two months earlier than what your schedule predicts. You can use a schedule compression technique, but management does not want to increase costs in the project. What approach would you recommend to condense the project duration?
Options
- AFast tracking
- BCrashing
- CEffort-driven activity analysis
- DRewards and recognition for the project team