Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent…
The correct answer is C. -$985,040. The schedule variance for a project can be found by subtracting the planned value from the earned value. In this instance, it would be as follows: =(0.859,850,400) - (0.959,850,400) = 8,372,840 - 9,357,880 Schedule variance (SV) is a measure of schedule performance on a…
Question
Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule variance for this project?
Options
- A$163,626
- B$130,901
- C-$985,040
- D0.16
How the community answered
(23 responses)- A4% (1)
- B4% (1)
- C78% (18)
- D13% (3)
Explanation
The schedule variance for a project can be found by subtracting the planned value from the earned value. In this instance, it would be as follows: =(0.859,850,400) - (0.959,850,400) = 8,372,840 - 9,357,880 Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that the schedule is ahead or behind what was planned for this period in time. The schedule variance is calculated based on the following formula: SV = Earned Value (EV) - Planned Value (PV) If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater than 0 shows that the project is ahead of the planned schedule. A value of 0 indicates that the project is right on target. Answer option B is incorrect. $130,901 is the cost variance. Answer option A is incorrect. $163,626 is the variance at completion for this project. Answer option D is incorrect. 0.16 is the difference between the schedule performance index of .84 and a perfect schedule.
Topics