PMI-SP · Question #142

You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?

The correct answer is B. Project schedule network diagram. Sequence Activities is one of the twenty processes of the Planning Process group. It is the process of identifying and documenting relationships among the project activities. Inputs Following are the inputs to this activity: Activity attributes Project scope statement…

Schedule Planning and Development

Question

You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?

Options

  • AProject scope statement
  • BProject schedule network diagram
  • CActivity list
  • DOrganizational process assets

How the community answered

(50 responses)
  • A
    2% (1)
  • B
    94% (47)
  • C
    4% (2)

Explanation

Sequence Activities is one of the twenty processes of the Planning Process group. It is the process of identifying and documenting relationships among the project activities. Inputs Following are the inputs to this activity: Activity attributes Project scope statement Organizational process assets Outputs Following are the outputs of the sequence activities process: Project schedule network diagrams Project document updates

Topics

#sequence activities#project schedule network diagram#process outputs#activity sequencing