PMI-SP · Question #142
You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?
The correct answer is B. Project schedule network diagram. Sequence Activities is one of the twenty processes of the Planning Process group. It is the process of identifying and documenting relationships among the project activities. Inputs Following are the inputs to this activity: Activity attributes Project scope statement…
Question
You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?
Options
- AProject scope statement
- BProject schedule network diagram
- CActivity list
- DOrganizational process assets
How the community answered
(50 responses)- A2% (1)
- B94% (47)
- C4% (2)
Explanation
Sequence Activities is one of the twenty processes of the Planning Process group. It is the process of identifying and documenting relationships among the project activities. Inputs Following are the inputs to this activity: Activity attributes Project scope statement Organizational process assets Outputs Following are the outputs of the sequence activities process: Project schedule network diagrams Project document updates
Topics
Community Discussion