Question
Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project to guide him and the project team through the estimate activity duration process. The previous project schedule could best described as which one of the following?
Options
- AOrganizational process asset
- BLessons learned documentation
- CProcess input
- DPredecessor project