PMI-SP · Question #144
Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project to guide him and the project team through the estimate activity duration process. The previous…
The correct answer is A. Organizational process asset. This is an example of an organizational process asset. The previous project is the historical information that the current project can use. This could also be, with a bit more information, an example of an analogous estimate. Organizational process assets are forms, templates…
Question
Gary is the project manager of the GHY project. He has elected to use a previous, but similar, project to guide him and the project team through the estimate activity duration process. The previous project schedule could best described as which one of the following?
Options
- AOrganizational process asset
- BLessons learned documentation
- CProcess input
- DPredecessor project
How the community answered
(44 responses)- A93% (41)
- B5% (2)
- D2% (1)
Explanation
This is an example of an organizational process asset. The previous project is the historical information that the current project can use. This could also be, with a bit more information, an example of an analogous estimate. Organizational process assets are forms, templates, and other support pieces that the project managers can use to help manage their projects. It is usually something that has been created before the project begins and often, but not always, comes from historical information. Answer option D is incorrect. This is not a valid term for this question. Answer option B is incorrect. The lessons learned documentation is a separate document that Gary might reference for his current project, but this is not a valid choice. Answer option C is incorrect. While organizational process assets are inputs to this process, this choice is not the best selection for