PMI-SP · Question #137
PMI-SP Question #137: Real Exam Question with Answer & Explanation
The correct answer is D. Risk register. Fast tracking allows phases of the project to overlap and increases risk for the project. When new risks are introduced into the project they should be recorded in the risk register. Risk register is a document that contains the results of the qualitative risk analysis, quantitat
Question
Options
- AOrganizational process assets
- BCost management plan
- CResource calendars
- DRisk register
Explanation
Fast tracking allows phases of the project to overlap and increases risk for the project. When new risks are introduced into the project they should be recorded in the risk register. Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning. Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the Answer option B is incorrect. The costs do not change because of the new fast tracking Answer option C is incorrect. Resource calendars show the availability of project resources. Answer option A is incorrect. Organizational process assets are updated as a result of updating the risk register when you consider that the risk register will become part of the organizational process assets. However, this is not the best answer for this question.
Community Discussion
No community discussion yet for this question.