nerdexam
PMI

PMI-SP · Question #131

Choose and reorder the essential steps required in developing the baseline schedule. Select an item from the right pane. Click button to move the selected item to the left pane. Click button to move…

The correct answer is C. (O+M+P)/6. You've hit your limit · resets 5:20am (America/New_York)

Schedule Planning and Development

Question

Choose and reorder the essential steps required in developing the baseline schedule. Select an item from the right pane. Click button to move the selected item to the left pane. Click button to move the item back to the right pane. Click and buttons to sort the list, if required. Answer:

Exhibits

PMI-SP question #131 exhibit 1
PMI-SP question #131 exhibit 2

Options

  • AO+M+P
  • B(O+M+P)/3
  • C(O+M+P)/6
  • DAverage of the estimates

How the community answered

(23 responses)
  • A
    9% (2)
  • C
    87% (20)
  • D
    4% (1)

Explanation

You've hit your limit · resets 5:20am (America/New_York)

Topics

#baseline schedule#schedule development process#schedule planning steps#project planning

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice