Question

You are the project manager for the GRT Project in your organization. You have created your time duration estimates based on historical information, but the estimates are not holding true in your current project. Unfortunately, many activities are late. You have decided to create a PERT estimate with your project team for each of their activities. What is the formula used for PERT?

Options

  • AO+M+P
  • B(O+M+P)/3
  • C(O+4M+P)/6
  • DAverage of the estimates