PMI-SP · Question #128
You work as the project manager for BlueWell Inc. You are recording the activity status for your project team's performance in the project. Based on the current performance your project is likely to…
The correct answer is D. Performance report. A performance report is needed to communicate the variance between planned work and actual work. A performance report is made by the project team detailing activities, milestones, problems, accomplishments, and identified issues. Performance reports are used to report some key…
Question
You work as the project manager for BlueWell Inc. You are recording the activity status for your project team's performance in the project. Based on the current performance your project is likely to be three months late. What type of communication should be generated based on this performance issue?
Options
- AIssue report
- BExceptions report
- CVariance analysis
- DPerformance report
How the community answered
(32 responses)- B3% (1)
- C3% (1)
- D94% (30)
Explanation
A performance report is needed to communicate the variance between planned work and actual work. A performance report is made by the project team detailing activities, milestones, problems, accomplishments, and identified issues. Performance reports are used to report some key information as follows: Current status Scheduled activities Significant accomplishment for the period Forecasts Issues Answer option A is incorrect. An issue report is not the best answer for this scenario. Issues are recorded in the issue log and an issue owner is assigned. Answer option B is incorrect. An exceptions report is a tempting answer as this is an exception to the project. PMI does not use this terminology. Answer option C is incorrect. Variance analysis is the activity of reviewing the variance to determine why it exists.