PMI-SP · Question #123

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. This project management process will create four outputs…

The correct answer is B. Schedule baseline. The schedule baseline is the only output of the develop schedule process among these answers. The three other outputs of the Develop Schedule Process are: project schedule, schedule data, and project document updates. Answer option D is incorrect. Activity duration estimates…

Schedule Planning and Development

Question

You are the project manager for your organization. You and the project team are developing the project schedule for your current project. This project management process will create four outputs. Which of the following is an output of the Develop Schedule process?

Options

  • AWork performance information
  • BSchedule baseline
  • CResource calendars
  • DActivity duration estimates

How the community answered

(18 responses)
  • A
    6% (1)
  • B
    94% (17)

Explanation

The schedule baseline is the only output of the develop schedule process among these answers. The three other outputs of the Develop Schedule Process are: project schedule, schedule data, and project document updates. Answer option D is incorrect. Activity duration estimates are an output of the Estimate Activity Duration process. Answer option A is incorrect. Work performance information is an input of the Control Schedule Answer option C is incorrect. Resource calendars are an input to the Develop Schedule process.

Topics

#develop schedule outputs#schedule baseline#PMBOK process outputs#schedule development