nerdexam
PMI

PMI-SP · Question #111

PMI-SP Question #111: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #111. The question stem and answer options stay visible for context.

Question

Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled to be 90 percent done by this date. She has spent $490,000 to date. What should Billy report as her cost performance index (CPI)for this project?

Options

  • A.07
  • B1.07
  • C$34,000
  • D.89

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice
Billy is the project manager of the PQW Project and she has an... | PMI-SP Q#111 Answer | NerdExam