nerdexam
PMI

PMI-SP · Question #156

Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is B. Project Plan Development C. Integrated Change Control D. Project Plan Execution. Project Integration Management is one of the nine Project Management Knowledge areas. It comprises the following processes: Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Direct and Manage Project Execution Monitor and…

Schedule Monitoring and Controlling

Question

Which of the following processes fall under the Project Integration Management knowledge area? Each correct answer represents a complete solution. Choose all that apply.

Options

  • AQuality Assurance
  • BProject Plan Development
  • CIntegrated Change Control
  • DProject Plan Execution

How the community answered

(32 responses)
  • A
    13% (4)
  • B
    88% (28)

Explanation

Project Integration Management is one of the nine Project Management Knowledge areas. It comprises the following processes: Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Direct and Manage Project Execution Monitor and Control Project Work Integrated Change Control These processes occur throughout the project and are repeated quite often during the working of the project. They ensure that the various elements of the project are properly coordinated. What are the Project Management Knowledge Areas? The Project Management Knowledge Areas are groupings that bring together processes that have things in common. For example, Resource Planning, Cost Estimating, Cost Budgeting, etc., are part of the Project Cost Management knowledge group. These processes may or may not be part of different or same process groups. Guide to the PMBOK identifies forty- two processes that are arranged in nine knowledge areas. The knowledge areas are as follows: Project Integration Management Project Scope Management Project Time Management Project Cost Management Project Quality Management Project Human Resource Management Project Communications Management Project Risk Management Project Procurement Management Answer option A is incorrect. Quality Assurance is a part of the Project Quality Management

Topics

#project integration management#integrated change control#PMBOK knowledge areas#project plan execution

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice