Don is the project manager of the NQP project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations…

The correct answer is C. Activity list and attributes. The activity list and the attributes will contain the information about the activities that interact with the government regulations. Answer option A is incorrect. The risk management plan communicates how the risks will be identified, analyzed, responded to, and monitored…

Schedule Planning and Development

Question

Don is the project manager of the NQP project for his organization. This project is scheduled to last for 18 months and will have several elements of the project that have government regulations. Management is concerned with the regulations and would like Don to report on the activities that will be affected by the regulations. Which of the following documents should Don refer to, for the information on the activities and the regulations?

Options

  • ARisk management plan
  • BActivity list
  • CActivity list and attributes
  • DRisk register

How the community answered

(52 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    88% (46)
  • D
    6% (3)

Explanation

The activity list and the attributes will contain the information about the activities that interact with the government regulations. Answer option A is incorrect. The risk management plan communicates how the risks will be identified, analyzed, responded to, and monitored. Answer option D is incorrect. The risk register is a list of all the risk events for the project. Answer option B is incorrect. The activity list is not a detailed enough answer for this question.