PMI-SP · Question #158
You are the project manager for your organization. You have been recording the actual results of activity duration for your project. Many of the results are late and this is causing your project to…
The correct answer is A. A schedule network analysis is performed using the schedule to compute the different. Of all the choices, the what-if scenario analysis allows you to determine the best approach to bring the schedule back into alignment with the project plan. What-if scenario analysis explains the analysis of the question "What if the situation represented by scenario 'X'…
Question
You are the project manager for your organization. You have been recording the actual results of activity duration for your project. Many of the results are late and this is causing your project to be late on reaching its milestones. What tool and technique can you use as a part of controlling the schedule to help you review various scenarios to bring the schedule into alignment with the plan?
Options
- AA schedule network analysis is performed using the schedule to compute the different
- BRoot cause analysis
- CSchedule analysis
- DResource leveling
How the community answered
(30 responses)- A77% (23)
- B7% (2)
- C3% (1)
- D13% (4)
Explanation
Of all the choices, the what-if scenario analysis allows you to determine the best approach to bring the schedule back into alignment with the project plan. What-if scenario analysis explains the analysis of the question "What if the situation represented by scenario 'X' happens?". This What-If Scenario Analysis shortly named as WIS scenarios, such as extending specific engineering durations, or delaying a major component delivery. Businesses use what-if scenarios to determine the effect different costs or investments have on profit and other financial indicators. Answer option D is incorrect. Resource leveling can cause your project's duration to increase. Answer option C is incorrect. Schedule analysis is the review of the schedule, but does not examine other possibilities for completing the project work. Answer option B is incorrect. Root cause analysis could help you determine the reasons why the project is running late, but it is not the best choice for this question as it is not a control schedule process tool and technique.