Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building…

The correct answer is D. External dependencies. An external dependency is any nonproject activity that is external to the project but has a direct impact on the project activities. An external dependency may be an inspector or any agency that may have to give prior approval before the project can move forward. Answer option…

Schedule Planning and Development

Question

Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

Options

  • AMandatory dependencies
  • BRequired dependencies
  • CDiscretionary dependencies
  • DExternal dependencies

How the community answered

(33 responses)
  • A
    3% (1)
  • C
    6% (2)
  • D
    91% (30)

Explanation

An external dependency is any nonproject activity that is external to the project but has a direct impact on the project activities. An external dependency may be an inspector or any agency that may have to give prior approval before the project can move forward. Answer option B is incorrect. Required dependency is not a valid term to describe a dependency. Answer option A is incorrect. Mandatory dependencies describe the required order in which the project work must take place - such as foundation before framing, or the operating system installed before the application may be installed. Answer option C is incorrect. Discretionary dependencies describe the optional order of the project work, such as painting the walls before installing the carpet.

Topics

#external dependencies#dependency types#activity sequencing#mandatory dependency