You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project. Which of the following statements is most accurate about…

The correct answer is A. Fast tracking only works if activities can be overlapped to shorten duration. Fast tracking is only valid if the activities or phases can be overlapped. Some activities or phases cannot be overlapped due to mandatory dependencies in the project. In other words, the work must be completed in a particular given order. Fast tracking is a technique for…

Schedule Monitoring and Controlling

Question

You are the project manager of the NAA Project for your organization. You are exploring the possibility of fast tracking in your project. Which of the following statements is most accurate about fast tracking the project?

Options

  • AFast tracking only works if activities can be overlapped to shorten duration.
  • BFast tracking only works if the activities are effort-driven.
  • CFast tracking only works if the activities are resource-driven.
  • DFast tracking only works if activities can have start-to-start relationships.

How the community answered

(32 responses)
  • A
    88% (28)
  • B
    3% (1)
  • C
    3% (1)
  • D
    6% (2)

Explanation

Fast tracking is only valid if the activities or phases can be overlapped. Some activities or phases cannot be overlapped due to mandatory dependencies in the project. In other words, the work must be completed in a particular given order. Fast tracking is a technique for compressing project schedule. In fast tracking, phases are overlapped that would normally be done in sequence. It is shortening the project schedule without reducing the project scope. Answer option C is incorrect. This is not a valid description of fast tracking. Answer option B is incorrect. Effort- driven or activities of fixed duration can be fast tracked. Answer option D is incorrect. The relationships among the activities do not have to be start-to-start to be fast tracked.

Topics

#fast tracking#schedule compression#activity overlap#schedule management