PMI-SP Exam Questions
328 real PMI-SP exam questions with expert-verified answers and explanations. Page 2 of 7.
- Question #62
Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule var...
- Question #63
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the proje...
- Question #64
Mary is the project manager for her company. She's working with the project team to compress the project schedule as the project must be completed by December 30. For some of the p...
- Question #65
Gary is the project manager for his organization. At each weekly status meeting with his project team, Gary collects information on the work that has been completed and reviews the...
- Question #66
You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good p...
- Question #67
Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs...
- Question #68
Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ult...
- Question #69
You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project...
- Question #70
Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedul...
- Question #71
You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen t...
- Question #72
You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You i...
- Question #73
Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project...
- Question #74
Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling c...
- Question #75
You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, t...
- Question #76
Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and sh...
- Question #77
You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an as...
- Question #78
You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter. They...
- Question #79
You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: Based on the project network diagram, how much float is availab...
- Question #80
You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?
- Question #81
Gary is the project manager of the NHF project, which is a part of a program in his organization. According to the PMBOK, how will Gary provide feedback to programs and portfolios?
- Question #82
You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project...
- Question #83
You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule...
- Question #84
Which of the following statements best describes an activity in a project?
- Question #85
Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his guidance. You, a team leader of a project, inform Fredrick about the performance in...
- Question #86
Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?
- Question #87
Jack works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complet...
- Question #88
You are the project manager of the NHG. The following figure represents your project network diagram. Management has asked that you add some features to the project scope. Through...
- Question #89
Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentati...
- Question #90
Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should...
- Question #91
You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a p...
- Question #92
You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some...
- Question #93
Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this techno...
- Question #94
You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following informati...
- Question #96
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know wha...
- Question #97
Lara has been assigned to a construction project. The project includes constructing a residential building with fifty flats. On which of the following events will the project be co...
- Question #98
You are the project manager of a research project. Because much of the project work will be based on what is discovered in each stage of the project work, you are directing the pro...
- Question #99
Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a sch...
- Question #100
You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets an...
- Question #101
Allen works as a project manager of the NHY project. This project is scheduled to last for two years and has a BAC of $5,400,000. He is currently 45 percent complete with this proj...
- Question #102
Which of the following is an output of the Identify Stakeholders process?
- Question #103
Examine the figure given below: You are the project manager of this project. Tom, a project team member, reports that Activity D will be delayed by 12 days due to the unavailabilit...
- Question #104
You work as a project manager for BlueWell Inc. You would like to crash your project to help the project schedule to get back on track. What is the primary danger of crashing?
- Question #105
You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining th...
- Question #106
You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen...
- Question #107
You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: Measureme...
- Question #108
You are the project manager of the NHQ project. You are working with your project team to create the project schedule and the project network diagram. In order to start the sequenc...
- Question #109
You work as a project manager for BlueWell Inc. Management has asked you to communicate with them whenever your project is about to reach a milestone so that they can review your p...
- Question #110
Beth works as a project manager for BlueWell Inc. Which of the following tools and techniques of Administer Procurements process will Beth use to manage contracts, and procurement...
- Question #111
Billy is the project manager of the PQW Project and she has an assigned project budget of $655,000. Currently she is 80 percent complete with the project though she was scheduled t...
- Question #112
Wendy is the project manager for the NHQ project. She is working with her project to begin creating the project duration estimate. Her organization is in weak matrix and several of...