- Question #51Stakeholder Communication
What is the term assigned to graphic in the figure given below?
communications bull's eyecommunication toolsstakeholder reportingreporting formats - Question #56Schedule Monitoring and Controlling
Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule var...
schedule varianceearned value managementSV formulaEV calculation - Question #57Stakeholder Communication
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure:
communications bull's eyerisk communicationstakeholder reportingcommunication tools - Question #62Schedule Monitoring and Controlling
Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule var...
schedule varianceearned value managementSV formulaEV calculation - Question #63Schedule Planning and Development
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: How much capital should the proje...
contingency reserveexpected monetary valuerisk quantificationrisk reserves - Question #64Schedule Planning and Development
Mary is the project manager for her company. She's working with the project team to compress the project schedule as the project must be completed by December 30. For some of the p...
crashingschedule compressioneffort-driven activitiesschedule optimization - Question #65Schedule Monitoring and Controlling
Gary is the project manager for his organization. At each weekly status meeting with his project team, Gary collects information on the work that has been completed and reviews the...
variance analysisschedule performance reviewschedule controllate work analysis - Question #66Schedule Planning and Development
You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good p...
crashingschedule compressionresource additionschedule optimization - Question #67Schedule Monitoring and Controlling
Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs...
schedule varianceearned value managementcrashing impactSV calculation - Question #68Stakeholder Communication
Tom works as the project manager for BlueWell Inc. He is working with his project to ensure timely and appropriate generation, retrieval, distribution, collection, storage, and ult...
communications managementinformation distributioninformation managementproject communications - Question #69Schedule Planning and Development
You are the project manager for your organization. Management has asked you to document the holidays, weekends, and other corporate working hours, which will supersede the project...
project calendarresource calendarorganizational calendarschedule planning - Question #70Schedule Monitoring and Controlling
Management is concerned about your project. They want to know how the project is performing specifically the schedule performance index. What formula do you use to find the schedul...
SPI formulaearned value managementschedule performance indexEVM formulas - Question #71Schedule Planning and Development
You work as a project manager for BlueWell Inc. You want to increase the overall duration of the project. If the management elects to use resource leveling, then what will happen t...
resource levelingproject durationresource optimizationschedule compression - Question #72Schedule Monitoring and Controlling
You work as a project manager for BlueWell Inc. Your project is falling behind though the project team reports that the actual durations of their work is what they estimated. You i...
corrective actionsschedule slippageschedule controlperformance monitoring - Question #73Schedule Planning and Development
Tom is the project manager of the GHQ Project for his organization. He is working on recovering the project schedule. As Tom examines his schedule he is especially aware of project...
soft logicdiscretionary dependenciesactivity sequencingschedule recovery - Question #74Schedule Monitoring and Controlling
Which of the following components of the change control system includes the documentation, tracking systems, and defined approval levels necessary for authorizing and controlling c...
configuration management systemchange controlintegrated change controldocumentation - Question #75Stakeholder Communication
You are the project manager for your organization. You are meeting with your customers to discuss the project performance. In this meeting, you will have eight project customers, t...
interactive communicationcommunication methodsstakeholder meetingscommunication channels - Question #76Schedule Monitoring and Controlling
Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and sh...
SPI calculationearned value managementschedule performance indexEVM calculations - Question #77Schedule Monitoring and Controlling
You are the project manager of the JKM Project for your organization. Your project is supposed to be 60 percent complete but you are only 45 percent complete. The project has an as...
CPI calculationearned value managementcost performance indexEVM calculations - Question #78Schedule Planning and Development
You are the project manager for the NHQ Project. Management has asked you to create a time estimate for this project although you have only just received the project charter. They...
ROM estimateanalogous estimatingproject charterduration estimating - Question #79Schedule Planning and Development
You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: Based on the project network diagram, how much float is availab...
float calculationnetwork diagramcritical path methodschedule analysis - Question #80Schedule Planning and Development
You are the project manager for your organization. You are working with your project team to create activity duration estimates using the PERT method. What is the formula for PERT?
PERT formulathree-point estimatingduration estimatingweighted average - Question #81Stakeholder Communication
Gary is the project manager of the NHF project, which is a part of a program in his organization. According to the PMBOK, how will Gary provide feedback to programs and portfolios?
program feedbackportfolio reportingstatus reportschange requests - Question #82Schedule Planning and Development
You are a project manager in a matrix environment and management is concerned about the utilization of the resources on your project team and when you'll release them. What project...
staffing management planresource releasehuman resourcesmatrix environment - Question #83Schedule Planning and Development
You are working as a project manager for BlueWell Inc. Which of the following tools and techniques of the Define Activity process will help you in identifying the typical schedule...
Define Activity processtemplatesschedule milestonesactivity identification - Question #84Schedule Planning and Development
Which of the following statements best describes an activity in a project?
activity definitionwork packageproject scopeWBS - Question #85Schedule Monitoring and Controlling
Fredrick works as a Project Manager for BlueWell Inc. A number of projects are running under his guidance. You, a team leader of a project, inform Fredrick about the performance in...
SPI interpretationschedule performance indexearned value managementperformance analysis - Question #86Schedule Planning and Development
Which of the group creativity techniques enhances brainstorming with a voting process used to rank the most useful ideas for further brainstorming or prioritization?
nominal group techniquegroup creativitybrainstormingidea prioritization - Question #87Schedule Monitoring and Controlling
Jack works as a project manager for the NHQ project. His project has a budget of $2,208,456 and is scheduled to last for three years. His project is currently forty percent complet...
ETC calculationEAC forecastingearned value managementbudget at completion - Question #88Schedule Monitoring and Controlling
You are the project manager of the NHG. The following figure represents your project network diagram. Management has asked that you add some features to the project scope. Through...
critical path methodnetwork diagramactivity duration changeschedule compression - Question #89Schedule Close-Out
Marty is the project manager of the recently completed NHK Project. The project was deemed successful by the project customer and they have signed the formal acceptance documentati...
project closurearchiving recordslessons learnedcloseout activities - Question #90Schedule Monitoring and Controlling
Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the project planning processes is now coming into fruition. What individual should...
risk ownerrisk responsestakeholder rolesrisk management - Question #91Schedule Planning and Development
You are the project manager for your organization. You are working on creating the activity list so that you can create the project schedule. This current project is similar to a p...
activity listschedule templatesparametric estimatesactivity attributes - Question #92Stakeholder Communication
You work as a project manager for BlueWell Inc. You are in the process of identifying all the people and organization impacted by the project. Mark, a project team member, has some...
identify stakeholdersproject charterstakeholder managementprocess inputs - Question #93Schedule Planning and Development
Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this techno...
project calendarschedule management plancalendar time periodsplanning documents - Question #94Stakeholder Communication
You are the project manager of the SWC project. You have created the stakeholder register. In the stakeholder register of your project, you will have all of the following informati...
stakeholder registerstakeholder classificationidentification informationassessment information - Question #95Schedule Planning and Development
Choose and reorder the essential steps required in developing the scheduling framework. Select an item from the right pane. Click button to move the selected item to the left pane....
scheduling frameworkschedule development processplanning sequenceschedule strategy - Question #96Schedule Monitoring and Controlling
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know wha...
SPIearned value managementschedule performance indexBAC - Question #97Stakeholder Communication
Lara has been assigned to a construction project. The project includes constructing a residential building with fifty flats. On which of the following events will the project be co...
project success criteriastakeholder expectationsproject completionacceptance - Question #98Schedule Planning and Development
You are the project manager of a research project. Because much of the project work will be based on what is discovered in each stage of the project work, you are directing the pro...
rolling wave planningprogressive elaborationactivity definitionresearch projects - Question #99Schedule Planning and Development
Holly is a new project manager in your organization. She is working with you on the JHG project and she is confused as to why the project needs a schedule management plan and a sch...
schedule management planschedule baselineschedule controlplanning documents - Question #100Schedule Planning and Development
You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets an...
activity sequencingprocess inputsproject scope statementmilestone list - Question #101Schedule Monitoring and Controlling
Allen works as a project manager of the NHY project. This project is scheduled to last for two years and has a BAC of $5,400,000. He is currently 45 percent complete with this proj...
schedule varianceearned valueEV calculationPV - Question #102Stakeholder Communication
Which of the following is an output of the Identify Stakeholders process?
identify stakeholdersstakeholder registerprocess outputsstakeholder management - Question #103Schedule Monitoring and Controlling
Examine the figure given below: You are the project manager of this project. Tom, a project team member, reports that Activity D will be delayed by 12 days due to the unavailabilit...
float analysisschedule delaycritical pathnetwork diagram - Question #104Schedule Monitoring and Controlling
You work as a project manager for BlueWell Inc. You would like to crash your project to help the project schedule to get back on track. What is the primary danger of crashing?
schedule compressioncrashingproject costsschedule recovery - Question #105Schedule Planning and Development
You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining th...
activity definitiondecompositionrolling wave planningtools and techniques - Question #106Schedule Monitoring and Controlling
You are the project manager for your organization. You are managing a project to create new software for your clients. During the project execution, there have been some unforeseen...
control scheduleprocess inputswork performance informationproject management plan - Question #107Schedule Monitoring and Controlling
You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: Measureme...
schedule varianceearned valueBCWPBCWS - Question #108Schedule Planning and Development
You are the project manager of the NHQ project. You are working with your project team to create the project schedule and the project network diagram. In order to start the sequenc...
milestone listactivity sequencingproject phaseskey deliverables