Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,2

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #76. The question stem and answer options stay visible for context.

Schedule Monitoring and Controlling

Question

Holly is the project manager of the NDS project and she is 85 percent complete with her project though she should be 95 percent complete. Her project has a BAC of $9,850,400 and she has spent $8,011,221 to date. What is Holly's schedule performance index for this project?

Options

  • A1.07
  • B0.98
  • C0.89
  • DTen percent

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#SPI calculation#earned value management#schedule performance index#EVM calculations