PMI-SP Exam Questions
328 real PMI-SP exam questions with expert-verified answers and explanations. Page 1 of 7.
- Question #1
You are the project manager of the NHQ Project. Management has set a conformance to the project schedule for your project at 0.95. What does this term mean?
- Question #2
Which one of the following estimate types is a form of expert judgment?
- Question #3
You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third...
- Question #5
Mark is the project manager of the GHQ Project. He is happily reporting that his project has a schedule performance index of 2.12. Management, however, does not think this is good...
- Question #6
You are the project manager of the BHG Project. You are creating a network diagram as shown in the figure: Mary, a project team member, reports that an identified risk is likely to...
- Question #7
Sam is the project manager of the NQQ project. He and the project team have completed the stakeholder identification process for his project. What is the main output of the identif...
- Question #8
You work as a project manager for BlueWell Inc. Management has asked you not to communicate performance unless the CPI is less than 0.96 or the SPI dips below 0.98. What type of re...
- Question #9
You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned. Considering that the proje...
- Question #10
Andy works as the project manager for Bluewell Inc. He is developing the schedule for the project. There are eight tools and techniques that a project manager can use to develop th...
- Question #11
You are the project manager for your organization. You have recorded the following duration estimates for an activity in your project: optimistic 20, most likely 45, pessimistic 90...
- Question #12
You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure: You are concerned about a risk on Activity G that if it happens...
- Question #13
Beth is the project manager for her organization. Her current project has many deliverables that have been defined at a high level, but the details of the deliverables are still un...
- Question #14
Gina is the project manager for her organization and she is working with her project team to define the project activities. In this project, the stakeholders are sensitive to the p...
- Question #15
You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the di...
- Question #16
John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure: Based on the project network diagram, how much float is avail...
- Question #17
Ben is the project manager for his organization. His project has 26 stakeholders this week and will have five additional stakeholders next week. How many more communication channel...
- Question #18
You are the project manager for your company. You are working with the activities defined in the figure below. What will happen to your project if Activity F takes five additional...
- Question #19
You are the project manager for your organization. You need the oak cabinets for your project delivered by December 1 in order to install the floors around the oak cabinets by Dece...
- Question #20
Your project has a BAC of $750,000 and is 75 percent complete. According to your plan, however, your project should actually be 80 percent complete. You have spent $575,000 of your...
- Question #21
You are the project manager of the NHT Project. This project has 12,345 office doors to install throughout a campus. Each of the doors costs the project $456 and requires special h...
- Question #22
Your project is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked that you report on the schedule variance for your proj...
- Question #23
Jim is the project manager for his project. He and his project team are creating their duration estimates for the work packages in the WBS. For each activity, Jim is adding a few h...
- Question #25
You work as a project manager for ABC Inc. You are currently overseeing a project on a high-rise building site. Your prime concern is to ensure that cranes are used effectively for...
- Question #26
John works as a project manager for BlueWell Inc. He is working on a high-profile project with 80 stakeholders and he needs to express to his project team and to the management the...
- Question #27
You work as a project manager for BlueWell Inc. There have been changes to the project scope in your project. These changes will cause the project schedule to change as well, so yo...
- Question #28
You have been hired as a project manager for Tech Perfect Inc. You are studying the documentation of planning of a project. The documentation states that there are twenty-five stak...
- Question #29
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project,...
- Question #30
The figure given below demonstrates the communication model for a project. What role does the component E play in the communications model?
- Question #31
Which of the following documents is a narrative description of products or services to be supplied by the project and has detailed requirements and pricing specified on it?
- Question #32
Fred is the project manager of the NHA project. This project has a BAC of $2,456,900 and is sixty percent complete. Fred has crashed the project, which has driven the project costs...
- Question #33
You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project,...
- Question #34
Which may be employed to shorten a schedule without changing the scope of the task?
- Question #35
Surveys have shown that the primary skill needed to be a project manager is communication skill. The typical project manager spends approximately ______percent of his or her time c...
- Question #36
A computer tape which contains historical project information is called ____ tape.
- Question #37
Risk event is the description of what may happen to the _____ of the project.
- Question #38
Which of the following is NOT part of stakeholder's management?
- Question #39
On what is project baseline development established?
- Question #40
Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know how Tom will r...
- Question #41
You have been assigned to a project that centers on a discipline you are only topically aware of. While you do have years of experience as a project manager, but you have never wor...
- Question #42
You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4...
- Question #43
Which organizational theory explains the factors that promote performance of people in any organization?
- Question #44
You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your p...
- Question #45
Harry works as the project manager for his organization. He is creating the activity list and would like to tag those activities that are comprised of apportioned effort. Which of...
- Question #46
You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You review these activities with your project team discovere...
- Question #47
You are the project manager of the OOI Project and you're forty percent complete with this project. The project has a BAC of $2,345,650 and you have spent $950,000 to date. Based o...
- Question #48
Which of the following individuals performs various management roles within an administrative or functional area of the business, such as human resources, finance, accounting, or p...
- Question #50
You are the project manager for your organization. You and the project team are developing the project schedule for your current project. In addition to the enterprise environment...
- Question #51
What is the term assigned to graphic in the figure given below?
- Question #56
Amy is working on a project which is forty percent complete though it was scheduled to be fifty percent complete as of today. Management has asked Amy to report on the schedule var...
- Question #57
You are the project manager of the GHE Project. You have identified the following risks with the characteristics as shown in the following figure: