Question
You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?
Options
- ATotal float is the amount of time an activity can be delayed without delaying any project
- BTotal float is the amount of time an activity can be delayed without delaying the project
- CTotal float is the amount of time an activity can be delayed without delaying the project
- DTotal float is the amount of time a non-critical activity can be delayed without delaying any