PMI-SP · Question #15

You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between…

The correct answer is B. Total float is the amount of time an activity can be delayed without delaying the project. Total float is the time you can delay an activity without delaying the project end date, whereas free float is on each activity and does not affect the early start date of successor activities. Float, also called slack, is the amount of time an activity can be delayed without…

Schedule Planning and Development

Question

You have created the project network diagram for the ABC project. You are exploring total float and free float for that project. Martin, a project team member, wants to know the difference between total float and free float. What is the difference between total float and free float?

Options

  • ATotal float is the amount of time an activity can be delayed without delaying any project
  • BTotal float is the amount of time an activity can be delayed without delaying the project
  • CTotal float is the amount of time an activity can be delayed without delaying the project
  • DTotal float is the amount of time a non-critical activity can be delayed without delaying any

How the community answered

(42 responses)
  • A
    2% (1)
  • B
    95% (40)
  • C
    2% (1)

Explanation

Total float is the time you can delay an activity without delaying the project end date, whereas free float is on each activity and does not affect the early start date of successor activities. Float, also called slack, is the amount of time an activity can be delayed without affecting any subsequent activities. There are two types of floats available: Free Float: It is the amount of time a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Total Float: It is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date, or violating schedule constraint. Float is calculated by using the critical path method technique. Answer options C, A, and D are incorrect. These are not accurate definitions of free float and total float.

Topics

#total float#free float#critical path method#schedule flexibility